1. Arrange delivery of flooring from Marshalls Timber. Delivery before 7.00am. (Unload onto footpath)
2. Move timber flooring into squash court, store on top floor on battens, asap.
(6 persons required.)
Wednesday13th June.
1. Mark position of floor joists and line markings onto squash walls. (Dick)
Friday 15nd June.
1a. Pick up floor sander from Bunnings or 4 Hire. (Sander for 4 hrs) (Grit 24)
Sanding edger (Graeme Bakker).
1.Remove court 2 door. Remove front wall tin & mesh. Rough sand floor. Clean & vacuum floor.
2. Return floor sander within the 4 hour limit. ( 5 persons required )
3.Lay, clue and screw down first board on the west wall. (Andrew)
Saturday 16th June.
1.Continue laying the new floor.
(5 persons)
Sunday 17th June.
1.Continue laying the new floor.
(5 persons)
Monday 18th June.
1.Complete laying the new floor.
2. Pick up floor sander
2.Sand floor, clean & vacuum the floor. (80/100 Grit Size)
3.Return floor sander (hire 4 hrs max)
(4 persons)
Tuesday 19th June.
1.Cut 10mm off the bottom of the door and paint the door.
2. Install new mesh and timber edging to front wall.
(3 persons)
Wednesday 20th June.
1.Mark out, tape and paint new line markings on the floor. Re-paint lines on front wall. (Tim & Jason)
2.Re-fit the squash door. Remove all rubbish and left over materials from squash courts.
Monday, 25th Court 2 re-open.